Skip to main content
Florida contractor answers

Florida rules, answered plainly

The lien, license, permit, and payment questions Florida contractors ask, with the statute named in every answer. This is general information, not legal advice.

Lien rights and the Notice to Owner

Florida's construction lien law is Chapter 713. Miss the Notice to Owner window on a job and the lien is gone, whatever you are owed.

Statutes citedFla. Stat. § 713.06(2)(a)Fla. Stat. § 713.011(1)Fla. Stat. § 713.18

Who has to send a Notice to Owner in Florida?

A lienor not in privity with the owner: subcontractors, sub-subcontractors, and material suppliers who contract with someone below the owner (Fla. Stat. § 713.06(2)(a)). Laborers are exempt, and a prime contractor who contracts directly with the owner does not serve an NTO because the owner already knows them.

The Florida Notice to Owner deadline, and how to track it
When does the 45-day Notice to Owner clock start in Florida?

It runs from your first furnishing, the first day that lienor furnishes labor, services, or materials, not from the overall project start and not from your last day of work (Fla. Stat. § 713.06(2)(a)). You can serve before you start, but no later than 45 days after.

The Florida Notice to Owner deadline, and how to track it
What happens if I miss the Florida Notice to Owner deadline?

By statute the failure to serve, or to timely serve, the NTO is a complete defense to enforcement of the lien by any person (Fla. Stat. § 713.06(2)(a)). It is a total loss of lien rights on that job, regardless of the amount owed. This is not legal advice; talk to a Florida construction attorney about your options.

The Florida Notice to Owner deadline, and how to track it
When is a Florida Notice to Owner considered served: on mailing or on delivery?

When you serve by registered or certified mail with evidence of delivery, Florida treats service as effective on the date of mailing, not the date of receipt (Fla. Stat. 713.18). So the postmark or mailing date is what satisfies the 45-day window. FL Permit Pay's worksheet is built around that mailing-date rule. This is not legal advice; confirm the service method that fits your job.

Notice to Owner software, built for Florida's Chapter 713
Does the Notice to Owner deadline extend if it falls on a weekend or holiday?

Yes. Under Fla. Stat. § 713.011(1), if the last day of a Ch. 713 period falls on a Saturday, Sunday, or legal holiday, the period extends to the end of the next business day. FL Permit Pay applies this roll-forward, but you should not rely on it to cut the deadline close.

The Florida Notice to Owner deadline, and how to track it

Your license, your qualifier, and your subs

Chapter 489 is what lets you contract in Florida. If the qualifier's license goes, the company's authority goes with it.

Statutes citedFla. Stat. § 489.119Fla. Stat. § 489.116Fla. Stat. § 489.128

When does my Florida contractor license expire?

Florida construction licenses renew biennially on August 31. Certified contractors renew in even-numbered years, registered contractors in odd-numbered years, and electrical contractors (under the separate ECLB) in even-numbered years, per DBPR's licensing FAQs. Because your cadence depends on your license type, FL Permit Pay tracks the exact date per license rather than assuming one global rule. Confirm your specific expiry at MyFloridaLicense.

Track your Florida contractor license renewal
What happens if my DBPR license lapses in Florida?

Under Fla. Stat. 489.116, a license not renewed at expiration goes delinquent, and if it stays unrenewed through the licensure cycle it becomes void by operation of law. While it is not current you are not authorized to contract, and contracting unlicensed carries penalties under Fla. Stat. 489.128. If your qualifier's license lapses, the business itself loses authorization (Fla. Stat. 489.119). The exact delinquent-to-void timeline is cycle dependent, so confirm your status on the state site.

Track DBPR licenses, COIs, and renewal dates
How does my qualifier affect my company's license renewal?

Your company contracts under a qualifying agent's license (Fla. Stat. § 489.119), so if that person's license lapses or they leave (starting a 60-day clock to replace them), the business loses its authorization to contract. That is why FL Permit Pay tracks the qualifier link and the qualifier's license expiry alongside the company's other credentials, not just the company name.

Track your Florida contractor license renewal
Can it confirm my license is actually active, or just remind me of the date?

It does both. Beyond the renewal reminder, License Verification matches your stored license against DBPR's official weekly construction extract and reads the Current plus Active status pair, stamping Verified active only when it truly is and showing the date pulled. It is a weekly extract, not real-time, so verify on the state site before you rely on it.

Track DBPR licenses, COIs, and renewal dates
How do I check whether a Florida subcontractor's licence is current?

Verify the licence against the Department of Business and Professional Regulation, which is the state's source of record for contractor licensure status. FL Permit Pay performs that verification and keeps the dated result on the subcontractor's credential record, so the check is evidence rather than a memory.

Tracking subcontractor licenses in Florida

Permits, review clocks, and inspections

Florida puts a deadline on the building official, not just on you. Section 553.792 is titled timely approval of building permits, and HB 803 (2026) added a new 5-business-day tier to it.

Statutes citedFla. Stat. § 553.792CS/CS/HB 803 (2026), Ch. 2026-63

How does the software track the HB 803 permit review deadline?

Enter the date the complete application went in and choose the review track. FL Permit Pay shows the applicable §553.792 estimate, pauses for requested corrections, and flags when the estimated window has passed. Confirm the result with the building department.

Florida permit tracking, from application to close-out
Does Florida permit tracking software pull my permit status automatically from Hillsborough, Pasco, or Pinellas?

No. Your team records the current permit and inspection status in FL Permit Pay. This works across Florida counties and keeps the county's wording with the job, but you still confirm live status in the county portal.

Florida permit tracking, from application to close-out
Does it cover counties outside Tampa Bay?

Yes, for tracking. Manual permit and inspection tracking works statewide across Florida's 67 counties. Sourced job-type pre-checks are currently verified for the mapped Tampa Bay counties (Hillsborough, Pasco, Pinellas); everywhere else you get Florida's statewide baseline plus the county's portal, clearly labeled as a baseline with a link to confirm.

Florida permit tracking, from application to close-out
Will it warn me before a permit expires?

Yes. Open permits that carry an expiration date surface on your command center as the date approaches, roughly 30 days out, then inside a week, then overdue, anchored to Florida time so a permit does not lapse before the job is finaled without warning.

Florida permit tracking, from application to close-out

Getting paid, retainage, and certified payroll

Public work in Florida has its own retainage and payment-timing rules, and federal money on a job brings the WH-347 with it.

Statutes citedFla. Stat. § 255.078Fla. Stat. § 218.73529 CFR 5.5(a)(3)(ii)

Does Florida cap how much retainage a contractor can hold back?

It depends on the project type. On state public construction, retainage is capped at 5% of each progress payment under Fla. Stat. § 255.078 (which does not apply if the total construction cost is $200,000 or less). On local-government public work, the cap is also 5% under Fla. Stat. § 218.735, with a 10% allowance for small municipalities and counties. On private projects, retainage is contract-driven and not statutorily capped (Fla. Stat. § 715.12), where market practice is commonly 5 to 10%. Confirm the figure against your contract and the statute; this is not legal advice.

How to get paid faster as a Florida contractor
When is payment legally due on a Florida public construction job?

Under the Local Government Prompt Payment Act (Fla. Stat. § 218.735), payment on a local-government job is generally due within 20 business days after the entity receives a proper invoice, or 25 business days if a third-party agent must approve it. A contractor who receives that payment must then pay its subs within 10 days. What counts as a proper invoice is defined by the contract, so confirm the terms before relying on the timer.

How to get paid faster as a Florida contractor
Does Florida require certified payroll or have a state prevailing-wage law?

No. Florida has no state prevailing-wage law. A WH-347 certified payroll is triggered only by federal or federally-assisted money on a project under the federal Davis-Bacon and Related Acts (contracts over $2,000). If your project has no federal funding, there is no WH-347 obligation, but confirm the funding source rather than assuming.

Review the weekly WH-347 record before certification
How often do I have to submit certified payroll?

Weekly. One payroll per workweek per project, numbered sequentially from 1, submitted within 7 days after the regular pay date with a signed Statement of Compliance (29 CFR 5.5(a)(3)(ii)). The prime contractor submits all subcontractors' payrolls, and records are kept 3 years after completion.

Review the weekly WH-347 record before certification
Can I collect the pay application online in Florida?

When online payment is active for your account, the GC or owner can pay by ACH or card on a hosted page and the money settles into your connected bank account. Check the availability shown in your account before offering it.

AIA G702 and G703 pay applications from field progress

Is this the right system for our company

What it is, what it costs to look at it, and what it will not do for you.

Is there a roofing CRM that also tracks Florida permits and inspections?

Yes. Each customer is attached to every job, and each job carries its permits and inspections. Run a sourced county pre-check, add the permit, move it from applied to final, and record inspection results. Your team enters permit status because FL Permit Pay does not pull live status from county portals.

A roofing CRM that also runs your Florida compliance
Can a construction CRM verify my DBPR contractor license?

FL Permit Pay matches your stored license against Florida DBPR's official weekly construction extract and stamps it Verified active only when the record is both Current and Active. It is a weekly extract, not a real-time lookup, and a license not in the file is shown as could not verify rather than a false green. It is not an official record, so confirm on the DBPR site before relying on it.

A roofing CRM that also runs your Florida compliance
Is my customer and job data private to my company?

Yes. Customers, jobs, permits, and documents are private to your company. You assign the roles that control who can view or edit customer records.

A roofing CRM that also runs your Florida compliance
Does a lead have to be retyped to become a job?

No. Converting a lead creates the customer and the job from the existing record, and a sent proposal or a won trigger advances the associated deal automatically, deduplicated by the job link.

Roofing lead management, from first call to signed job
Can I try it before I move real work into it?

Yes. Creating an account starts a 14-day trial with 3 seats and no card. Run one real job all the way through, from the proposal to the permit to the pay application, and decide from that. Nothing else has to move until you are satisfied it holds up.

Can I move over from Roofr, JobNimbus, or AccuLynx?

Yes, for customers, jobs, and your price book. The importer takes a CSV, shows you the source rows, and lets you check the field mapping before a single record is created. There is a dedicated Roofr jobs and catalog import.

Is every feature and integration on the pricing page live today?

No, and we label which is which instead of showing one checkmark for everything. Included, metered, setup-required, access-gated, and planned are separate states on the pricing and integrations pages. Supplier ordering with ABC Supply, SRS, and QXO is planned and is not connected today.

Still not the answer you needed?

Ask about your jobs.

Ask us directly