Count the days the county has had your permit.
On the Permit & Compliance plan, $149 a month. Put the whole crew on it. Nobody pays per person.

Fla. Stat. §553.792
County review clock
No county status sync
- Applied date
- Status
- In review, entered by your team
- Review scenario
- 30-day residential (sample)
- Permit fee
- $2,500.00
This is an example. We built it from the dates you typed. We take your applied date as the day the county got a complete application. We do not check it. A written waiver is recorded on the permit when you mark one, and a waived permit is never reported as late.
Residential · structure under 7,500 sq ft
- Estimated due date
- Status
- On track · 20 business days remain
Day count
- Allowed
- 30 business days
- Elapsed
- 10 weekdays
- Remaining
- 20 business days
- Fee reduction (modeled)
- 0% · not past the estimate
Public holidays are not subtracted; the count uses weekdays only. Once the clock runs late, the number shown is a modeled potential fee reduction to confirm with the department.
Five review scenarios. The one you pick stays an estimate.
| # | Scenario | Business days | Citation |
|---|---|---|---|
| 01 | Single-family · single-trade · under $15kExisting single-family dwelling, work under $15,000, one trade (roofing, electrical, plumbing, mechanical, gas, etc.), using a local-government plans reviewer. | 5 | §553.792(1)(a)1, new under HB 803 |
| 02 | Master / site-specific permitMaster building permit or site-specific permit under §553.794. | 12 | §553.792(1)(a) |
| 03 | CDBG-Disaster Recovery single-familySingle-family dwelling by a state-licensed contractor under a CDBG-DR program. | 10 | §553.792(1)(a) |
| 04 | Residential · structure under 7,500 sq ftResidential units / accessory / single-trade work on a structure under 7,500 sq ft. | 30 | §553.792(1)(a) |
| 05 | Large / commercial / multifamilyStructure 7,500 sq ft or larger; nonresidential under 25,000 sq ft; multifamily up to 50 units; site plans, plats, lot grading. | 60 | §553.792(1)(a) |
With no scenario chosen, the clock uses the 30-business-day default. The new 5-day tier takes effect July 1, 2026, but our source does not settle whether it covers permits already pending, so confirm before applying it to a specific permit.
The clock runs, pauses, or stops with the permit status.
Submitted or in review
The clock starts once your team enters the applied date.
Corrections
The clock pauses. A fresh clock after corrections is not modeled.
Decided or later
Approved, issued, inspections, finaled, expired, or void stops the clock.
5 business days on the new HB 803 tier
Say it is single-trade work under $15,000 on a house that already stands. If a local plans reviewer looks at it, the shot clock is five business days.
HB 803 added this tier on top of the existing 553.792 deadlines. Knowing which tier a permit sits on is the difference between waiting and following up.
Sourced to Fla. Stat. §553.792, as amended by HB 803. Confirm current requirements with the issuing authority.